Project Consortium Workplan Deliverables Dissemination Events Contact
Deliverables

The deliverables that are planned to be submitted for review to EC are listed in the table below. All deliverables, except the public ones, require an internal access. The nature of the deliverable is characterised by one of the following codes: R = Report, P = Prototype, D = Demonstrator, O = Other. The dissemination level complies with the following codes:

PU = Public
PP = Restricted to other programme participants (including the Commission Services)
RE = Restricted to a group specified by the consortium (including the Commission Services)
CO = Confidential, only for members of the consortium (including the Commission Services)
 
 No. Deliverable name Nature  Level  Delivery month 
 
D1.1 Signed consortium agreement R PP 2
D1.2 Steering and Technical committees members list R CO 2
D1.3 First semester steering committee meeting minutes R CO 6
D1.4 Second semester steering committee meeting minutes R CO 12
D1.5 First year report R PP 13
D1.6 Third semester steering committee meeting minutes R CO 18
D1.7 Fourth semester steering committee meeting minutes R CO 24
D1.8 Second year report R PP 25
D1.9 Fifth semester steering committee meeting minutes R CO 30
D1.10 Sixth semester steering committee meeting minutes R CO 36
D1.11 Final project report R PP 36
D2.1 Mission requirements compilation document R CO 6
D2.2 Optical sensor specification – version 1 (including sensor performance model) R CO 7
D2.3 End to end GNC performance report – version 1 R CO 11
D2.4 Optical sensor specification – version 2 R CO 11
D2.5 Sensor assessment protocol on the ground-test bench – version 1 R CO 11
D3.1 Scenario-based optical sensor system design R CO 7
D3.2 Sensor building-blocks list and specifications R CO 14
D3.3 Building-blocks interface definition R CO 14
D3.4 Functional tests description report R CO 15
D4.1 Test bench description R CO 12
D4.2 Test facilities capabilities assessment results R CO 18
D4.3 Test facilities up and running according to testing protocols O CO 20
D4.4 Guidelines to build a sensor prototype adapted to test facilities R CO 20
D4.5 Sensor assessment protocol in the ground-test facilities – version 2 R CO 23
D5.1 Building-blocks description R CO 18
D5.2 Building-blocks functional characterization test results R CO 28
D5.3 Sensor assessment protocol in the ground-test facilities – version 3 R CO 29
D5.4 Sensor functional test results R CO 30
D5.5 Sensor prototype up and running for the test bench R CO 30
D5.6 Sensor prototype user manual for assessment in ground-test facilities R CO 30
D6.1 Sensor assessment guidelines R CO 30
D6.2 Sensor prototype assessment results R CO 36
D7.1 Preliminary project web site description R CO 7
D7.2 First web site version up and running R PU 9
D7.3 Preliminary exploitation plan R CO 11
D7.4 Exploitation plan R CO 28